WRITTEN QUESTION TO THE MINISTER FOR TREASURY AND RESOURCES … BY DEPUTY J.A. MARTIN OF ST. HELIER … ANSWER TO BE TABLED ON TUESDAY 6th NOVEMBER 2012 … With regard to the answers provided …
-
WRITTEN QUESTION TO THE MINISTER FOR TREASURY AND RESOURCES … BY DEPUTY J.A. MARTIN OF ST. HELIER … ANSWER TO BE TABLED ON TUESDAY 6th NOVEMBER 2012 … With regard to the answers provided …
-
Answer The project has a budget of £21.07m, which is to be funded through the following allocations: Unspent Project Budget £19,070,000 Allocation 2013 £1,000,000 Allocation …
-
Answer i. The building comprises basement, ground, first, second and third floors together with a small element of accommodation at fourth floor level …
-
Answer On the 1st September, 2012, a private landowner in the area wrote to the Chief of Police with the offer of secure off-road private parking which could be used for staff …
-
Answer (a) The proposal is to locate archive storage, oversized vehicle parking and garage at a Statesowned warehouse-type location at La Collette … It should be noted that the …
-
WRITTEN QUESTION TO THE MINISTER FOR TREASURY AND RESOURCES … BY DEPUTY J.A. MARTIN OF ST. HELIER … ANSWER TO BE TABLED ON TUESDAY 6th NOVEMBER 2012 … With regard to the answer provided to …
-
WRITTEN QUESTION TO THE MINISTER FOR TREASURY AND RESOURCES … BY DEPUTY J.A. MARTIN OF ST. HELIER … ANSWER TO BE TABLED ON TUESDAY 6th NOVEMBER 2012 … Please would the Minister explain the …
-
Would the Minister advise whether there will be any access through Green Street Cemetery to the new Police Headquarters … Would he confirm the commencement date for the works on site …
-
WRITTEN QUESTION TO THE MINISTER FOR TREASURY AND RESOURCES … BY DEPUTY J.A. MARTIN OF ST. HELIER … ANSWER TO BE TABLED ON TUESDAY 12th MAY 2015 … Will the Minister provide an update of …
-
Answer The funding for these sites is included in the borrowing arrangements, as described in R15/2013, the Full Business Case which supports the Report and Proposition for the …
-
Would the Minister also give a list (using a map if necessary) of the other potential sites considered for the substation and explain, in each case, why the site was ruled out …